Contract Agreement Amount

Rs. 9,51,239

Physical Progress

100.00%

Financial Progress

99.98%

Remaining Payment

Rs. 0

Road Widening and ugrading works on Halchhap Kapahiti Sadak Bhaktapur

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 27-Nov-20

Start Date: 27-Nov-20

Completion Date: 11-Mar-2021 (EOT Not Done)

Project Description

No description available.