Contract Agreement Amount
Rs. 52,23,779
Physical Progress
100.00%
Financial Progress
99.98%
Remaining Payment
Rs. 0
Road widening &upgrading works at Dakchhin Barahi Chwamu Tole Balkot Panityanki Saraswati Mandir Dhadikot Rajkulo Road
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 10-May-21
Start Date: 10-May-21
Completion Date: 27-Sep-2021 (EOT Not Done)
Project Description
No description available.