Contract Agreement Amount

Rs. 2,66,05,256

Physical Progress

0.00%

Financial Progress

99.98%

Remaining Payment

Rs. 0

Supplying and Fixing Street Light.] from Chainage 19+500 km- 24+000 km, 10+915km - 11+550km to and 0+750km - 4+100km

Office: ब्यापारिक मार्ग बिस्तार आयोजन, बेलहिया बुटवल सडक , रुपन्देही (133)

Fiscal Year: 077-78

0.00%

Contract Date: 22-Dec-20

Start Date: 5-Jan-21

Completion Date: 18-Jan-2022 (EOT Done)

Project Description

No description available.