Contract Agreement Amount

Rs. 1,65,26,685

Physical Progress

47.73%

Financial Progress

99.98%

Remaining Payment

Rs. 0

Road Side Maintenance Work in Anarkholi-patan-jhulaghat section NH-03, khodpe- Chainpur Section NH 64

Office: सडक डिभिजन, तनहुं (25)

Fiscal Year: 079-80

47.73%

Contract Date: 9-Nov-22

Start Date: 9-Nov-22

Completion Date: 13-May-2023 (EOT Not Done)

Project Description

No description available.