Contract Agreement Amount
Rs. 34,60,600
Physical Progress
99.98%
Financial Progress
99.97%
Remaining Payment
Rs. 0
Recurrent (Reactive)Maintenance works (62+000-85+000)(Cn:RDSKT/337310113/077/78/7)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 077-78
Contract Date: 11-Nov-20
Start Date: 11-Nov-20
Completion Date: 14-Mar-2021 (EOT Not Done)
Project Description
No description available.