Contract Agreement Amount

Rs. 10,87,615

Physical Progress

0.00%

Financial Progress

99.97%

Remaining Payment

Rs. 0

Upgrading Worls along Udayapurko Mainamaini Wasepla Bhojpurko Hasanpur Ghodetar Bhojpur Sadarmukam Hudai Sankhuwasabha Jodne Sadak. Kiwar to Jholunge Pul (Ch.0+000 to 0+310) Bhojpur

Office: डिभिजन सडक कार्यालय, तुम्लीङटार, संखुवासभा (174)

Fiscal Year: 076-77

0.00%

Contract Date: 1-Nov-20

Start Date: 1-Nov-20

Completion Date: 13-Apr-2021 (EOT Not Done)

Project Description

No description available.