Contract Agreement Amount

Rs. 60,27,580

Physical Progress

99.96%

Financial Progress

99.96%

Remaining Payment

Rs. 0

Drain and Pavement works on Sangetada Dausur Pundada Kushapani Kalikot Road (Ch. 0+000 to 8+000 Km), Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

99.96%

Contract Date: 1-Nov-19

Start Date: 8-Nov-19

Completion Date: 12-Apr-2020 (EOT Not Done)

Project Description

No description available.