Contract Agreement Amount

Rs. 17,66,500

Physical Progress

100.00%

Financial Progress

99.96%

Remaining Payment

Rs. 0

Road Improvement Works at Hirapur Barrage Haripurwa Hajariya Sadak, Sarlahi

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 077-78

100.00%

Contract Date: 1-Dec-20

Start Date: 1-Dec-20

Completion Date: 27-Mar-2021 (EOT Not Done)

Project Description

No description available.