Contract Agreement Amount

Rs. 1,91,49,248

Physical Progress

100.00%

Financial Progress

99.96%

Remaining Payment

Rs. 0

Construction RCC Bridge over Jharne River

Office: शहीद मार्ग सडक योजना, रोल्पा (93)

Fiscal Year: 072-73

100.00%

Contract Date: 14-Jul-16

Start Date: 15-Jul-16

Completion Date: 13-Jan-2021 (EOT Done)

Project Description

No description available.