Contract Agreement Amount
Rs. 61,78,382
Physical Progress
100.00%
Financial Progress
99.95%
Remaining Payment
Rs. 0
Blacktopped Road Construction Works including Cross - drainage Structures along Rauwamai Na.Pa. 06 Budhabare Bajar Om Budhabare Bajar Om Kareswar Shiva Mandir Shibalay Chowk Ananta Chowk Sanischare bajar, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 076-77
Contract Date: 20-Nov-19
Start Date: 20-Nov-19
Completion Date: 12-May-2020 (EOT Done)