Contract Agreement Amount

Rs. 44,49,995

Physical Progress

99.93%

Financial Progress

99.93%

Remaining Payment

Rs. 0

Pavement works Including Retaining Structures along Gramthan - 7 Bajarangbali- Nahar - Belbari - Bahuni Sadak Road, Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

99.93%

Contract Date: 22-Mar-22

Start Date: 22-Mar-22

Completion Date: 14-Jan-2023 (EOT Done)

Project Description

No description available.