Contract Agreement Amount
Rs. 24,26,140
Physical Progress
100.00%
Financial Progress
99.91%
Remaining Payment
Rs. 0
Reactive Maintenance Works along Birendrachowk-Bijneta Section in Dang District.
Office: योजना तथा अनुगमन महाशाखा (सडक सुरक्षा तथा ट्राफिक शाखा) (5)
Fiscal Year: 078-79
Contract Date: 5-Dec-22
Start Date: 5-Dec-22
Completion Date: 13-Apr-2023 (EOT Not Done)
Project Description
No description available.