Contract Agreement Amount

Rs. 43,81,798

Physical Progress

100.00%

Financial Progress

99.91%

Remaining Payment

Rs. 0

Improvement of Tallo Garjamani- Asaina- Sikalpatti –Thada -Jonapur- Dhakaniya -Ranipur- Basantpur-Bansaha-Ganeshpur-Deepnagar-Amarpur-Naukhuri-Manikadham Road, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 076-77

100.00%

Contract Date: 29-Nov-19

Start Date: 14-Dec-19

Completion Date: 31-Oct-2020 (EOT Done)

Project Description

No description available.