Contract Agreement Amount

Rs. 5,42,43,845

Physical Progress

95.00%

Financial Progress

99.87%

Remaining Payment

Rs. 0

Construction of Black top, structure, cross drainage & roadway excavation at Sanfebagar/Ghughurkot - Tuka Khand road section.

Office: सेति लोकमार्ग (टिकापुर​, लोडे, चैनपुर​, ताक्लाकोट​) सडक योजना, अछाम (197)

Fiscal Year: 076-77

95.00%

Contract Date: 3-Jan-20

Start Date: 3-Jan-20

Completion Date: 02-Jan-2021 (EOT Not Done)

Project Description

No description available.