Contract Agreement Amount
Rs. 72,58,571
Physical Progress
0.00%
Financial Progress
99.84%
Remaining Payment
Rs. 0
Construction of RCC Bridge over Nala-01(Bire Khola) along Birganj- Thori Road, Parsa
Office: हुलाकी राजमार्ग आयोजना, योजना कार्यालय, वीरगंज, पर्सा (168)
Fiscal Year: 070-71
Contract Date: 8-Jul-13
Start Date: 8-Jul-13
Completion Date: 10-Oct-2014 (EOT Not Done)
Project Description
No description available.