Contract Agreement Amount
Rs. 32,94,415
Physical Progress
99.81%
Financial Progress
99.81%
Remaining Payment
Rs. 0
Pavement Works along Milan Chowk Paschim Uttar Dhimal tole jane Sadak Urlabari 01, Morang
Office: सडक डिभिजन, वुटवल (28)
Fiscal Year: 080-81
Contract Date: 25-Jan-24
Start Date: 25-Jan-24
Completion Date: 08-Jul-2024 (EOT Not Done)
Project Description
No description available.