Contract Agreement Amount
Rs. 3,36,19,720
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Rehabilitation and Maintenance Works on Dumre-Besisahar Road (24+000 to 42+800)
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 076-77
Contract Date: 26-May-20
Start Date: 26-May-20
Completion Date: 29-Sep-2020 (EOT Not Done)
Project Description
No description available.