Contract Agreement Amount
Rs. 16,23,86,129
Physical Progress
99.80%
Financial Progress
99.80%
Remaining Payment
Rs. 0
Construction of RCC Bridge over Jogbuda nadi on Dodara chadani na.pa. 7 Panchabhoj ,Kanchanpur
Office: सडक डिभिजन, कञ्चनपुर (34)
Fiscal Year: 073-74
Contract Date: 4-Jun-17
Start Date: 4-Jun-17
Completion Date: 07-Sep-2021 (EOT Done)
Project Description
No description available.