Contract Agreement Amount
Rs. 1,26,90,000
Physical Progress
100.00%
Financial Progress
99.80%
Remaining Payment
Rs. 0
Protection Works at Lakhandehi Bridge on Sundarpur Bhlehi Road, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 077-78
Contract Date: 23-Mar-21
Start Date: 23-Mar-21
Completion Date: 24-Jul-2021 (EOT Not Done)
Project Description
No description available.