Contract Agreement Amount
Rs. 3,10,13,552
Physical Progress
0.00%
Financial Progress
0.00%
Remaining Payment
Rs. 100
Rehabilitation and Improvement Works at Harisiddhi Ma.Vi.-Naya Basti-Thaiba Chowk
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 075-76
Contract Date: 24-Jun-19
Start Date: 24-Jun-19
Completion Date: 11-Apr-2021 (EOT Done)
Project Description
No description available.