Contract Agreement Amount
Rs. 2,16,03,531
Physical Progress
0.00%
Financial Progress
99.79%
Remaining Payment
Rs. 0
Panauti Khopasi Taaldhunga Road , Kavre (Road uppgrading Works)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 2-Jan-20
Start Date: 2-Jan-20
Completion Date: 12-Jun-2020 (EOT Not Done)
Project Description
No description available.