Contract Agreement Amount
Rs. 5,19,62,859
Physical Progress
0.00%
Financial Progress
99.79%
Remaining Payment
Rs. 0
Rigid Pavement & Roadway Improvement Works at Hilepani Halesi Sector Ch.10+360-39+990
Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)
Fiscal Year: 072-73
Contract Date: 25-May-16
Start Date: 25-May-16
Completion Date: 12-Apr-2020 (EOT Done)
Project Description
No description available.