Contract Agreement Amount

Rs. 5,19,62,859

Physical Progress

0.00%

Financial Progress

99.79%

Remaining Payment

Rs. 0

Rigid Pavement & Roadway Improvement Works at Hilepani Halesi Sector Ch.10+360-39+990

Office: Puspalal (Midhill) Road Project, Kavrepalanchok (274)

Fiscal Year: 072-73

0.00%

Contract Date: 25-May-16

Start Date: 25-May-16

Completion Date: 12-Apr-2020 (EOT Done)