Contract Agreement Amount
Rs. 92,51,181
Physical Progress
99.80%
Financial Progress
99.78%
Remaining Payment
Rs. 0
Construction of Road structures and Earthworks from Bohokhor(Ch. 47+000)to pali,khagadri (Ch.53+000)
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 076-77
Contract Date: 8-Dec-19
Start Date: 8-Dec-19
Completion Date: 04-Feb-2021 (EOT Done)
Project Description
No description available.