Contract Agreement Amount

Rs. 31,36,240

Physical Progress

99.21%

Financial Progress

99.76%

Remaining Payment

Rs. 0

Road Rehabilitation works on Sanfe-Bayalpata Road Section, Achham

Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)

Fiscal Year: 080-81

99.21%

Contract Date: 24-Sep-23

Start Date: 24-Sep-23

Completion Date: 14-Jan-2024 (EOT Not Done)

Project Description

No description available.