Contract Agreement Amount
Rs. 31,36,240
Physical Progress
99.21%
Financial Progress
99.76%
Remaining Payment
Rs. 0
Road Rehabilitation works on Sanfe-Bayalpata Road Section, Achham
Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)
Fiscal Year: 080-81
Contract Date: 24-Sep-23
Start Date: 24-Sep-23
Completion Date: 14-Jan-2024 (EOT Not Done)