Contract Agreement Amount

Rs. 4,20,74,492

Physical Progress

0.00%

Financial Progress

99.76%

Remaining Payment

Rs. 0

Jhagadu Chowk Belhi Bajar Sripur Katani Murtiya hudai Hariwonko chini mill gate Sadak, Sarlahi (Chainage 0+000 to 3+500)

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 076-77

0.00%

Contract Date: 3-May-20

Start Date: 3-May-20

Completion Date: 08-Jan-2021 (EOT Done)

Project Description

No description available.