Contract Agreement Amount

Rs. 5,25,15,114

Physical Progress

99.75%

Financial Progress

99.74%

Remaining Payment

Rs. 0

Roadway Excavation,Structure and Gravel works on Surkhet-Jumla Road Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

99.75%

Contract Date: 3-Mar-20

Start Date: 6-Mar-20

Completion Date: 04-Mar-2021 (EOT Not Done)

Project Description

No description available.