Contract Agreement Amount
Rs. 60,43,480
Physical Progress
0.00%
Financial Progress
99.73%
Remaining Payment
Rs. 0
Construction of RCC Retainging WallWith Rock Anchorage on Siddhartha Highway.(At CH-28+600)
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 076-77
Contract Date: 3-Feb-20
Start Date: 18-Feb-20
Completion Date: 13-Jan-2021 (EOT Done)