Contract Agreement Amount
Rs. 13,01,700
Physical Progress
0.00%
Financial Progress
99.72%
Remaining Payment
Rs. 0
Pipe Culvert Maintenance and Gabion Works on Vyas Marga(20+000 to 24+000)
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 077-78
Contract Date: 2-Nov-20
Start Date: 2-Nov-20
Completion Date: 30-Jan-2021 (EOT Not Done)