Contract Agreement Amount

Rs. 31,26,810

Physical Progress

100.00%

Financial Progress

99.71%

Remaining Payment

Rs. 0

Rigid Pavement Works along Kalaiya Nagarpalika ward-12 Sitalpur Chowk dekhi Kalaiya Na. Pa. ward-20 Basatpur Road, Bara

Office: सडक डिभिजन, पाल्पा (27)

Fiscal Year: 079-80

100.00%

Contract Date: 3-Jan-23

Start Date: 3-Jan-23

Completion Date: 13-Jun-2023 (EOT Not Done)

Project Description

No description available.