Contract Agreement Amount

Rs. 30,42,544

Physical Progress

100.00%

Financial Progress

99.71%

Remaining Payment

Rs. 0

Construction of Retaining Structures and Hume Pipe Works upto Gravel Standard on Bohoretar-Shikharkateri-Deurali-Kotgau Road section, Sindhuli

Office: सडक डिभिजन, वुटवल (28)

Fiscal Year: 079-80

100.00%

Contract Date: 12-Apr-23

Start Date: 12-Apr-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.