Contract Agreement Amount

Rs. 1,31,21,080

Physical Progress

99.69%

Financial Progress

99.69%

Remaining Payment

Rs. 0

Roadway Excavation,Structure and Pavement works on Bangesimal-Badichaur-Uuppalosyaulekhand Section(Surkhet-Jumla)Ch:0+000-39+000 Km

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

99.69%

Contract Date: 30-Jun-20

Start Date: 30-Jun-20

Completion Date: 12-Apr-2021 (EOT Not Done)

Project Description

No description available.