Contract Agreement Amount
Rs. 60,81,019
Physical Progress
100.00%
Financial Progress
99.69%
Remaining Payment
Rs. 0
Construction of Black Topped Road at Birtamode Na.Pa. Muktichowk - Sanischare - Jaipur - Budhabare Sadak, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 076-77
Contract Date: 8-Nov-19
Start Date: 8-Nov-19
Completion Date: 13-May-2020 (EOT Not Done)
Project Description
No description available.