Contract Agreement Amount
Rs. 5,51,930
Physical Progress
0.00%
Financial Progress
99.68%
Remaining Payment
Rs. 0
Road Maintenance works on ARM (Adarsha - Jagate)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 075-76
Contract Date: 28-May-19
Start Date: 28-May-19
Completion Date: 30-Jun-2019 (EOT Not Done)
Project Description
No description available.