Contract Agreement Amount
Rs. 2,16,04,082
Physical Progress
0.00%
Financial Progress
99.66%
Remaining Payment
Rs. 0
Construction of RCC Bridge Samri Khola Nuwakot
Office: Puspalal (Midhill) Road Project, Gorkha (275)
Fiscal Year: 072-73
Contract Date: 21-Aug-16
Start Date: 21-Aug-16
Completion Date: 18-May-2019 (EOT Done)