Contract Agreement Amount

Rs. 37,45,037

Physical Progress

99.66%

Financial Progress

99.66%

Remaining Payment

Rs. 0

Chhamling Bridge Protection Works

Office: गाईघाट दिक्तेल सडक योजना, उदयपुर (63)

Fiscal Year: 076-77

99.66%

Contract Date: 7-Nov-19

Start Date: 7-Nov-19

Completion Date: 04-Jul-2020 (EOT Not Done)