Contract Agreement Amount
Rs. 36,95,482
Physical Progress
87.00%
Financial Progress
99.66%
Remaining Payment
Rs. 0
Traffic safety works at Araniko Rajmarga NH-34, Mude- Khadichaur Road NH-23 and Bandeu- Chautara Road NH-31, Sindhupalchowk
Office: डिभिजन सडक कार्यालय, चितवन (20)
Fiscal Year: 079-80
Contract Date: 30-Nov-22
Start Date: 30-Nov-22
Completion Date: 15-Jun-2023 (EOT Not Done)
Project Description
No description available.