Contract Agreement Amount
Rs. 34,02,640
Physical Progress
100.00%
Financial Progress
99.66%
Remaining Payment
Rs. 0
Reactive Maintenance Works at Paththarkot to Chakla Section (CH 9+500-30+000), along Gorusinge-Sandhikharka Road,
Office: योजना तथा अनुगमन महाशाखा (योजना अनुगमन तथा मुल्यांकन शाखा) (3)
Fiscal Year: 080-81
Contract Date: 6-Nov-23
Start Date: 6-Nov-23
Completion Date: 03-Feb-2024 (EOT Not Done)
Project Description
No description available.