Contract Agreement Amount

Rs. 1,24,95,308

Physical Progress

100.00%

Financial Progress

99.65%

Remaining Payment

Rs. 0

Road Construction Works on Basai- Fataiya-Matiya- Bandatal -Khiriya- Butabari- Belauri- Daiji Road, Kanchanpur (Chainage 0+000 to 1+470 from Jaman Singh Bhandari Chowk)

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 076-77

100.00%

Contract Date: 25-Jun-20

Start Date: 2-Jul-20

Completion Date: 28-Mar-2021 (EOT Not Done)

Project Description

No description available.