Contract Agreement Amount

Rs. 28,59,84,955

Physical Progress

91.60%

Financial Progress

99.65%

Remaining Payment

Rs. 0

Design and Build of Lal Bakaiya River Bridge, Gunahi- Inaewa, Rautahat

Office: पुल योजना, मध्य क्षेत्र सेक्टर नं. २, काठमाण्डौ (189)

Fiscal Year: 072-73

91.60%

Contract Date: 18-Sep-16

Start Date: 18-Sep-16

Completion Date: 14-Jul-2022 (EOT Done)

Project Description

No description available.