Contract Agreement Amount

Rs. 22,65,610

Physical Progress

88.00%

Financial Progress

99.63%

Remaining Payment

Rs. 0

Road Safety works at Mude-Khadichaur Road NH 23-009 and Araniko Highway NH-34, Sindhupalchowk

Office: सुदुरपच्चिमाञ्चल क्षेत्रिय सडक निर्देशनालय, डोटी (11)

Fiscal Year: 080-81

88.00%

Contract Date: 7-Nov-23

Start Date: 7-Nov-23

Completion Date: 03-Mar-2024 (EOT Not Done)

Project Description

No description available.