Contract Agreement Amount
Rs. 9,47,06,996
Physical Progress
99.58%
Financial Progress
99.58%
Remaining Payment
Rs. 0
Construction of Prestressed RCC Bridge over Bakraha Khola Bridge,Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 071-72
Contract Date: 14-Jul-15
Start Date: 14-Jul-15
Completion Date: 13-Mar-2020 (EOT Done)