Contract Agreement Amount

Rs. 7,26,95,838

Physical Progress

0.00%

Financial Progress

99.54%

Remaining Payment

Rs. 0

Asphalt Concrete overlay at Khaniyakharka -Khurkot of Dhulikhel-Sindhuli-Bardibas Road

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 076-77

0.00%

Contract Date: 22-Dec-19

Start Date: 7-Jan-20

Completion Date: 12-Jun-2020 (EOT Not Done)

Project Description

No description available.