Contract Agreement Amount

Rs. 87,43,02,137

Physical Progress

100.00%

Financial Progress

99.53%

Remaining Payment

Rs. 0

Widening of Yamdi Bridge- Ghatte Khola Section of Pokhara-Baglung Road ( Km 6+000 to 12+000) in Kaski District

Office: Puspalal (Midhill) Road Project, Parbat (276)

Fiscal Year: 074-75

100.00%

Contract Date: 11-Sep-17

Start Date: 12-Sep-17

Completion Date: 07-Jan-2022 (EOT Done)

Project Description

No description available.