Contract Agreement Amount

Rs. 1,10,02,444

Physical Progress

0.00%

Financial Progress

99.51%

Remaining Payment

Rs. 0

Maintenance and Painting works along Belahiya - Butwal Road from Chainage Km 0+750- 24+000.

Office: ब्यापारिक मार्ग बिस्तार आयोजन, बेलहिया बुटवल सडक , रुपन्देही (133)

Fiscal Year: 077-78

0.00%

Contract Date: 22-Nov-20

Start Date: 22-Nov-20

Completion Date: 22-Jan-2022 (EOT Done)

Project Description