Contract Agreement Amount
Rs. 1,10,02,444
Physical Progress
0.00%
Financial Progress
99.51%
Remaining Payment
Rs. 0
Maintenance and Painting works along Belahiya - Butwal Road from Chainage Km 0+750- 24+000.
Office: ब्यापारिक मार्ग बिस्तार आयोजन, बेलहिया बुटवल सडक , रुपन्देही (133)
Fiscal Year: 077-78
Contract Date: 22-Nov-20
Start Date: 22-Nov-20
Completion Date: 22-Jan-2022 (EOT Done)