Contract Agreement Amount
Rs. 6,32,14,038
Physical Progress
0.00%
Financial Progress
99.51%
Remaining Payment
Rs. 0
Construction of Simply Supported, 40 m span,cast in situ, Prestressed Concrete Bridge over Tadi Khola, Nuwakot
Office: डिभिजन सडक कार्यालय, नुवाकोट (21)
Fiscal Year: 074-75
Contract Date: 15-Mar-18
Start Date: 29-Mar-18
Completion Date: 09-Jul-2021 (EOT Done)
Project Description
No description available.