Contract Agreement Amount
Rs. 42,58,060
Physical Progress
0.00%
Financial Progress
99.50%
Remaining Payment
Rs. 0
Roadway Upgrading Works on Shringapath marga, Tanahun (Ch: 18+150 to 18+525).
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 076-77
Contract Date: 10-Jan-20
Start Date: 10-Jan-20
Completion Date: 25-May-2020 (EOT Done)
Project Description
No description available.