Contract Agreement Amount
Rs. 75,02,480
Physical Progress
99.50%
Financial Progress
99.50%
Remaining Payment
Rs. 0
Road Structure and Retaining Wall works on surkhet-Jumla Road Dailekh(CH:RDSKT/33701138-4/077/78-10)
Office: सडक डिभिजन, सुर्खेत (33)
Fiscal Year: 077-78
Contract Date: 29-Nov-20
Start Date: 29-Nov-20
Completion Date: 12-Apr-2021 (EOT Not Done)
Project Description
No description available.