Contract Agreement Amount
Rs. 3,06,40,820
Physical Progress
100.00%
Financial Progress
99.48%
Remaining Payment
Rs. 0
Roadway Upgrading Works on Bhimad RampurMityal Arungkhola Road(Ch 12+000 to 22+800), Tanahun
Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)
Fiscal Year: 079-80
Contract Date: 14-Oct-22
Start Date: 14-Oct-22
Completion Date: 05-Jul-2023 (EOT Not Done)
Project Description
No description available.