Contract Agreement Amount

Rs. 7,77,21,450

Physical Progress

0.00%

Financial Progress

99.47%

Remaining Payment

Rs. 0

Asphalt Concrete and Miscellaneous Works at Banepa Sindhuli Bardibas Road

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 075-76

0.00%

Contract Date: 11-Jun-19

Start Date: 24-Jun-19

Completion Date: 19-Mar-2021 (EOT Done)

Project Description

No description available.