Contract Agreement Amount

Rs. 1,04,78,689

Physical Progress

100.00%

Financial Progress

99.46%

Remaining Payment

Rs. 0

Road Upgrading Works on Pandubazar Chok(ARM) Pandubazar-Height-Ganeshman-Singh-Batika Gundu Bus Park Pipaldaada Dadhikot Jaane Sadak

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 4-Apr-21

Start Date: 4-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)